Penjadwalan proyek pengembangan software secara dinamis dan multi proyek dengan pendekatan heuristik

Jurnal Teknologi & Manajemen Informatika, Volume 4, Nomor 1, April 2006
Journal from JIPTUNMERPP / 2009-01-08 19:48:22
Oleh : Bambang Nurdewanto ; Rully Soeliman , Faculty of Information Technology Merdeka University Malang
Dibuat : 2006-04-01, dengan file

Keyword : Effort, schedule, COCOMO II, multi-project, heuristic.

Prior to the implementation of software development project it is commonly performed some estimation, such as: how much times taken to perform the project (scheduling), what efforts made to conduct it, and how many people (staffs) will be involved in the project execution. Using the method of COCOMO II, certain software can be estimated its needs of efforts and schedules. Knowing the efforts and schedules, a multi-project timetable can be established for some software being developed. So far, estimates of times and staffing in dynamic and multi-projected manner are difficult to calculate. Therefore, it is necessary to find the solution with heuristic approach. Comparing several heuristic approaches the most optimal solution can be searched. If there is a change in the schedule, then all the project activities will be rescheduled rapidly.

Deskripsi Alternatif :

Prior to the implementation of software development project it is commonly performed some estimation, such as: how much times taken to perform the project (scheduling), what efforts made to conduct it, and how many people (staffs) will be involved in the project execution. Using the method of COCOMO II, certain software can be estimated its needs of efforts and schedules. Knowing the efforts and schedules, a multi-project timetable can be established for some software being developed. So far, estimates of times and staffing in dynamic and multi-projected manner are difficult to calculate. Therefore, it is necessary to find the solution with heuristic approach. Comparing several heuristic approaches the most optimal solution can be searched. If there is a change in the schedule, then all the project activities will be rescheduled rapidly.

Copyrights : Copyright (c) 2009 by Digital Library Universitas Merdeka Malang. Verbatim copying and distribution of this entire article is permitted by author in any medium, provided this notice is preserved.

Beri Komentar ?#(0) | Bookmark

PropertiNilai Properti
ID PublisherJIPTUNMERPP
OrganisasiF
Nama KontakDra. Wiwik Supriyanti, SS
AlamatJl. Terusan Halimun 11 B
KotaMalang
DaerahJawa Timur
NegaraIndonesia
Telepon0341-563504
Fax0341-563504
E-mail Administratorperpus@unmer.ac.id
E-mail CKOwsupriyanti@yahoo.com

Print ...

Kontributor...

  • Editor: Wiwik Supriyanti, Dra. SS.